Minister of Energy and Mineral Development Dr. Canon Ruth Nankabirwa has expressed gratitude for the unwavering support from the local leadership and communities of the Kigezi region towards the growth of the energy sector in the country.

Nankabirwa made the remarks at the official Commissioning of 132KV Transmission Mirama-Kabale power Line in Kigazi Subregion.
Nankabirwa highlighted the project’s significance in enhancing power stability, supporting rural electrification, and driving socio-economic development.
“Today we are witnessing the commissioning of a transformative project that will significantly enhance power stability in Southwestern Uganda, particularly in the Kigezi sub-region” Nankabirwa said adding that this project will in addition to delivering electricity, create opportunities for industrial growth, improved livelihoods, and contribute to the nation’s overall economic development”.
Meanwhile, Ministry of Energy Permanent Secretary, Eng. Irene Bateebe, emphasized the significance of the Mirama-Kabale project in supporting Uganda’s energy transition and economic growth.
Bateebe outlined the key technical components of the project, including the construction of an 85km, 132kV steel tower transmission line and the establishment of two 132/33kV substations in Kabale and Mirama, both crucial for improving power supply stability and supporting rural electrification.
She also highlighted the project’s role in laying the groundwork for regional interconnections with neighbouring countries, contributing to cross-border energy trade.
“I would like to urge all stakeholders, including local governments and the communities, to actively safeguard the infrastructure by adhering to the Right-of-Way regulations and promoting awareness on the importance of maintaining buffer zones to prevent power outages and infrastructure vandalism” She urged.
The project traverses through Ntungamo, Rukiga, Kabale, and Rubanda districts was financed by the Islamic Development Bank (IsDB) with a loan of USD 83.75 million under the oversight of the Ministry of Energy and Mineral Development.
The project is expected to significantly reduce technical losses improve voltage regulation and provide reliable power to local industries and communities enhancing overall economic development in the region.
The Mirama-Kabale Transmission Line and Substations Project is a key achievement in Uganda’s ongoing efforts to expand its energy infrastructure, with further transmission projects planned to improve power reliability and connectivity across the country.

The Mirama-Kabale 132KV Transmission Line and other Associated Substations project at Hamuko,Kabale Substation in Kigezi Subregion was officially commissioned by Gen Yoweri Kaguta Museveni who is in Kigezi Subregion on PDM zonal tour.