Weyonje! KCCA ED Hajat Buzeki Engages Kasanvu  Locals In Clean-up Exercise, Condemns Construction Of Illegal Structures! 

Hajat Sharifah Buzeki speaking to the press as Eng. Akankwasa listens

By Sadique Bamwita 

The Executive Director Kampala Capital City Authority (KCCA), Hajat Sharifah Buzeki spent Saturday morning in Kasanvu zone in Makindye Division, engaging community members in a clean- up exercise which lasted for hours. 

During the clean-up dubbed ‘Weyonje’, she castigated developers who erect illegal structures without seeking building permission and proper architectural plan from the authority.

Hajat Buzeki vehemently warned locals against littering garbage along the road, in drainage channels and Infront of their frontages. 

On this note, she advised locals to sort out degradable and non-degradable wastes and put them in separate polythene bags for KCCA trucks to collect them.

Hajat Buzeki also appealed to locals to be vigilant following the outbreak of Ebola disease, on top of reporting anyone suspected to have signs of ebola disease.

In regards to the  building which collapsed on June 5,2026 in Kisaasi/Kisoota zone, Hajat Buzeki said the developer didn’t have an approved plan from the Authority, and that is why it had to collapse because all the construction works was Sub-standard.

“The construction was illegal and the developer never sought an approved building plan from the Authority. We shall take the owner to court for being non compliant with the required building procedures in addition to causing loss of lives, ” Hajat Buzeki vowed.

On the other hand, the Director engineering and technical services at KCCA, Eng. Akankwasa noted that the collapsed building was an illegal structure, the authority stopped it’s construction but the owner defied it and he went ahead to construct during night hours.

Eng. Akankwasa added that preliminary findings indicate that the Columns were built with weak materials hence the foundation was too weak to support the whole building.

“Poor materials and designs led to the collapse of the building. To make matters worse, there were no professionals to supervise the construction works” he said.