UEGCL To Spend USD7.2m To Procure Weed Harvester, Floating Boom To Save Nalubaale, Kiira Dams As Water Levels Rise

CHAIRED MEETING: ERA board chairperson Dr. Wasagali Sarah Kanaabi

Uganda Electricity Generation Company Limited (UEGCL) is planning to spend USD7,247323 in the coming year 2024, to procure a weed harvester and floating boom to manage the floating island on Lake Victoria.


It should be remembered that in 2020, a floating island invaded the Owen falls dam also known as Nalubaale and Kiira and it took several days for government to remove it hence disrupting the plant operations.


Now, according to UEGCL Chief Operations Officer, George Tusingwire, this company fully owned by government is planning to spend this money on the two critical items, hence its application for Tariff adjustment by the Electricity Regulatory Authority. ERA according to the law, is mandated to determine and announce annual electricity tariffs.


“Due to raising water levels, floating island need to be monitored to ensure that there’s no disruption of plant operations. More efforts in form of a boom and a weed harvester are needed” he said.


He was speaking at the Public Hearing of the Annual Tariff Review for 2024 organized by Electricity Regulatory Authority (ERA) at Imperial Royale.
UEGCL is among the four power companies including UETCL, UEDCL and Umeme that have placed applications to ERA for Tariff Review for 2024 citing various budget plans they want to undertake in the coming year.


Tusingwire said that when the floating island came in 2020, it came with a lot of gardens and these went and clogged the intake parts.
“We had to shut down those intakes to remove those weeds. Fishermen, UNRA, Army all came to help us and it took us 10 days to remove the material. If that happens again, people will have to turn to generators and it’s very disruptive to the economy” he told the hearing chaired by ERA board chairperson Dr. Sarah Wasagali Kanaabi.

GAVE ASSURANCE ON LICENSES: ERA C.E.O Eng. Ziria Tibalwa Waako


He said UEGCL looked for a permanent solution to the challenge and decided to have both a weed harvester and a boom.
“We have to put a barrier (floating boom) to trap all that material before it enters the intakes. We already have one at Bujagali and we want one for Karuma and Isimba. As for weed harvester, we recently procured one and its at Isimba” he said.


UEGCL also said it intends to spend a staggering Shs2.77bn to enhance salaries for former staff of Eskom whom the company retained after the departure of the South African company which was managing Nalubaale and Kiira plants but it’s contract expired.

ENTER UETCL

Meanwhile, Uganda Electricity Transmission Company Limited, also defended itself on perceived failure to evacuate generated power resulting into huge costs paid for by the tax payer in deemed energy costs.
Deemed energy occurs when power is generated at the source but it is not consumed because there are no transmission line (s) to take it away.


In the process, the government pays the investor huge sums of money annually in such unused energy, one of the recent cases being that of Pader-based Achwa Hydro Power Plant where government has been paying USD24million annually since 2019 until last month when a transmission line was commissioned.

Participants at the public hearing


However, according to Jenkins Miiro, the Acting head-commercial at UETCL, the deemed energy only arises under situations like when the private developer moves faster than UETCL. Besides; he said, UETCL takes a lot of time on settling compensation disputes.
“But the good news is that, that power (Achwa) is now evacuated” he said.


He said the company in the coming year, expects to undertake various projects among which is the completion of the Gulu-Oliyo-Nebbi line.
He said this line is very critical for government as it is aimed at ensuring that West Nile subregion is connected to the national grid. Other projects include completion of Bujagali -Tororo line aimed at increasing capacity of supplying electricity to Kenya, increase transformer capacity, reduction of transmission losses and dealing with vandalism of lines and substation equipment which he said is still a big challenge to the company.


“Installation capacity is expected to increase by 10% following additional 2 units at Karuma. From the current 1.805.4MW, we shall have 2015.7MW once the additional 2 units at Karuma are commissioned” he said.

ABOUT THE PUBLIC HEARING

According to Dr. Wasagali, ERA received four applications from the four companies. The purpose of the hearing was to enable stakeholders make comments on the applications and also for the licensees to make justification for the tariffs they have applied for.


“This will help ERA to a decision on the tariffs for 2024. This is part of the consultation process in line with ERA’s principle of transparency and involving the public to participate” she explained.
She said the core focus areas for customers include affordability of power, reliability, quality of service, access to power, demand growth and sustainability.


“We shall soon announce the base tariff for 2024 before the new year. Very soon, it will be Christmas, so I urge all licensees (to ensure) that there is reliable, safe and efficient service in all we’re doing” she said.


ERA’s CEO Eng. Ziria Tibalwa Waako, also allayed public fears that with the planned merger or government agencies including the power companies, this will affect licenses for licensed power companies.


“What will change is corporate identity. The licenses will remain in place. What will change is the structure. So, irrespective of whether we continue operating the way we’re structured or change, the licensing will not change” she said.