Proactive! KCCA ED Sharifah Buzeki Updates Public On Progressive Works On Allen, Ssebaana Roads

By Sadique Bamwita

Kampala

Kampala Capital City Authority (KCCA) Executive Director Hajati Sharifah Buzeki has issued a public notice updating the general public on the progressive construction works taking place along Allen and Ssebaana roads in Kampala City.

In a statement issued on November 10,2025 states, Buzeki stated that;

“On Saturday November 8, 2025, we closed off Allen Road and Ssebaana Road.

To date, KCCA engineers together with Kiham Enterprise engineering team have successfully cut, installed, and cast seven (7) channel crossings with 900mm diameter culverts to enhance storm-water flow into the Nakivubo Channel. These crossings are spread out from Shauriyako to Container Village’.

Buzeki added that next phase of the works involve the construction of inspection chambers to be completed by 15th November 2025. 

She explained that these will facilitate proper maintenance and long-term functionality of the drainage network.

“Reinstatement of the carriageway at the culvert crossings shall be progressively done to allow businesses operate during the day with minimal interruption and be completed by 30th November 2025” she said.

She went on, 

‘In conclusion, KCCA appreciates the cooperation of road users, traders, and the general public during this period and we remain committed to ensuring that Kampala develops into a safer, flood-resilient, and climate-ready City.’